Procurement of Installation Material for Mount Bawakaraeng Telemetry System telemetry

  • Buyer : Japan Radio Corp
  • User : Balai Sungai Pompengan-Jenebarang
  • Contract Number : OXA0022A/B
  • Contract Amout : Rp.  370.886.000,-
  • Date : 7 October 2010
  • Duration : 2 months
  • Location : South Sulawesi

One hill on the Bawakaraeng Mountain is  slided at 2007. The landslide in millions cubic meters of sedimentation is fullfilling jeneberang river and the Bili-Bili Dam.

Some sabo dams is constructed to reduce sedimentation which is shallowing the Bili-Bili Dam. Debris warning system is also developed to anticipate debris from the  upstream.

PT Sartika Mitrasejati is contracted for procurememt of installation material of the Telemetry System including grounding  and outdoor installation material

Scope : procurememt of grounding material for all stations, procurememt outdoor installation material including  installation of direct burried cable in 3 locations.